Delays in power supply agreements (PSAs) for 7 GW of the bid out renewable energy projects is one of the main reasons that may lead to 35% shortfall in 160 GW renewable energy capacity target set for calendar 2022-end, CRISIL has stated.
"This delay may, however, not impact the credit profile of developers since implementation and debt drawdowns have not yet started and project viability remains largely intact, supported by benign module price trajectory over past 18 months.
These projects were auctioned by central counterparties - the Solar Energy Corporation of India and the National Thermal Power Corporation - and are awaiting PSAs with the ultimate counterparties, the state distribution companies (discoms)," the rating agency has noted.

Says Hetal Gandhi, Director, CRISIL Research, "The PSAs for the 7 GW of projects bid out at auctions prior to February 2020 are yet to be signed primarily because subsequent auctions saw tariffs plummeting and even falling below Rs 2 in December 2020. Of this, nearly 3 GW run the risk of re-auction or cancellation because their tariffs are comparatively higher at over Rs 2.75 per unit - a good 75 paise more than the recently discovered tariffs."
The remaining 4 GW may have some hope because CRISIL expects 25-50 paise increase in tariffs at the upcoming auctions because new projects will have to bear basic customs duty applicable on import of solar cells and solar modules2. That means the tariff differential between projects sans PSAs but with tariffs below Rs 2.753, and those to be auctioned next, will narrow. It would also be faster for discoms, already short on their renewable targets, to buy power from auctioned projects with unsigned PSAs compared to projects which are yet to be auctioned.
Says Ankit Hakhu, Director, CRISIL Ratings, "The delays in the signing of PSAs, however, are unlikely to have a major impact on the credit profiles of renewable energy developers. That's because financial closure and debt drawdowns in such projects happen only upon the receipt of the Letter of Award, which is typically issued only after the PSAs are signed. As for project cost, no impact is foreseen because the prices of solar modules, which account for over 50% of it, have been benign."
More From GoodReturns

ATM Rules Changing From April 1, 2026: HDFC Bank, PNB, Bandhan Bank & Others Revise Cash Withdrawal Rules

Crash in Gold Rate in India by Rs 71,400 in Single Day; Will Gold Price Today Fall Below Rs 1.50 Lakh? Outlook

Gold & Silver Rates Today Live: MCX Gold Crashes By Rs 5,645, Silver Falls By Rs 16,540; 24K, 22K, 18K Gold

1:5 Split Soon? Vedanta Ltd To Consider 3rd Interim Dividend On March 23, Share Jumps; Record Date & Buy Call

Sleeper Vande Bharat Express New Routes Identified for Long Distance Travel

Gold & Silver Rates Today Live Updates: Will 24 Carat, 22 Carat, 18 Carat See Bullish Week Ahead?

Mega Gold Price Crash Alert! 24K Sinks Rs 1.36 Lakh/100 Gm In Week; Silver Sees Losses | March 23-27 Outlook

Gold & Silver Rates Today Live: MCX Gold Ends Above Rs 1.40 Lakh, Silver Up 1%; 24K, 22K, 18K Gold On March 24

Gold Rate Crashes Over Rs 1 Lakh in Single Day, Slips to Lowest Since January; Will Gold Price Today Decline?

Gold Price Crash May Fuel Jewellery Demand: Why Kalyan Jewellers Share Price Could Shine Despite 5% Dip

Fatal Crash In Gold Rates In India By Rs 1,03,200/100 Gm; Biggest Single-Day Fall In 24K, 22K, 18K Gold Prices



Click it and Unblock the Notifications