The first phase of the Noida International Airport, estimated to cost Rs 10,056 crore, is nearing completion with 70% of the work done. The airport is set to open for operations by September 2023.
The upcoming international airport in Noida, Uttar Pradesh, is progressing steadily with the first phase of development set to be completed by September 2024. The project, estimated to cost Rs 10,056 crore, has already seen an investment of around Rs 7,100 crore, covering over 70% of the financial expenditures.

Progress Review and Completion Target
S P Goyal, Additional Chief Secretary to the Uttar Pradesh Chief Minister, recently reviewed the progress of the airport and emphasized the importance of meeting the completion deadline. The first phase of the airport, spread across 1,300 hectares, is scheduled to commence flight operations by September this year.
Key Developments and Infrastructure
During the review meeting, officials from Yamuna International Airport Private Limited (YIAPL), the concessionaire for the greenfield airport, provided updates on the ongoing construction work. The terminal building, ATC tower, and runway are being constructed by EPC contractor Tata Projects as per the development plan.
YIAPL informed that additional machinery and workforce have been deployed at the airport site to ensure timely completion of the project. The concessionaire assured the officials that the airport construction will be finished within the stipulated timeframe.
Financial Details and Phase 1 Capacity
OSD Shailendra Bhatia, who is also the additional CEO of the Yamuna Expressway Authority, revealed that the total expenditure for the first phase of the airport development stands at Rs 10,056 crore. Out of this, approximately Rs 7,100 crore has been spent so far, covering land acquisition and development.
In its initial phase, the airport, designated with the code DXN, will feature a single runway and a terminal building capable of handling 12 million passengers annually.
The Noida International Airport project is a significant infrastructure development that will enhance connectivity and boost economic growth in the region. With the first phase nearing completion, the airport is poised to become a major transportation hub, catering to both domestic and international travelers.
More From GoodReturns

Gold Rate in India Slips Around Rs 26,000/24K in Single Day Amid Escalating Iran-Israel, US Tension; Outlook

Gold Rates In India Today Crash By Rs 31,100, Third Fall This Week; 24K, 22K, 18K Gold Prices On March 4

Gold Rates & Silver Rates Today Live: MCX Gold & Silver Price To Open Volatile After Holi; 24K, 22K, 18K Gold

Happy Women's Day 2026: Top 50+ Wishes, Messages, Quotes, Captions, Greetings, Status To Share On March 8

Fall in Gold Rate in India Continues; 24K/100gm Plunges Rs 85,800 in Just 3 Days; MCX Gold Price Flat; Outlook

Gold Rate Today: Gold Prices Crash Over Rs 1 Lakh per 24K/100g in 4 Days Amid Iran-Israel Conflict; Outlook

Gold Rate in India Takes U-Turn! 24K Jumps Rs 23,000 In Day! Silver Stable After Weak US Jobs Data | March 7

4:1 Bonus + 2:1 Stock Split + Rs. 12 Dividend: 3 Stocks to Watch as They Turn Ex-Date On March 9

Gold Rates In India Today March 6, 2026: Gold Rate Crash Fifth Day In Row By Rs 1,09,800; 24K, 22K, 18K Gold

Gold Rates & Silver Rates Today Live: MCX Gold & Silver May Take Hit On Inflationary Fear; 24K, 22K, 18K Gold

Gold Rate Today, 9 March Outlook: Rise in Gold Prices in India After Falling Nearly Rs 1.2 Lakh Per 24K/100gm



Click it and Unblock the Notifications